Manually Enter Specific Weightage Percent on Summary MS Project

Farihin Marzuki 0 Reputation points
2026-09-17T01:42:36.1966667+00:00

Hi, can I manually insert specific weightage percent on summary task in MS Project? For example, the percentage of weightage for each section should be as follows:-

  1. Engineering in YELLOW = 20%
  2. Procurement in GREEN = 8%
  3. Construction in BLUE  = 60%
  4. Comm in RED    = 7%
  5. IA in ORANGE       = 5% Total                    = 100%
Microsoft 365 and Office | Project | For business | Windows
0 comments No comments

1 answer

Sort by: Most helpful
  1. Elena-VH 1,650 Reputation points Independent Advisor
    2026-09-17T02:29:07.62+00:00

    Dear Farihin Marzuki,

    I understand that you would like to assign specific weightages to each project phase. Unfortunately, Microsoft Project does not allow you to manually enter a weighted percentage directly on a Summary Task and have the built-in % Complete field use those values. Summary task progress is calculated automatically based on the progress of its underlying subtasks.

    As a workaround, If you are using the Microsoft Project desktop application, you can create a custom Number field (for example, Number1) to store the weightage for each summary section. You can then use another custom field with a formula to calculate the weighted contribution of each section based on its actual % Complete. The weighted values can then be summed to determine the overall project progress. For reference: Create a custom field in Project

    Note: If you are using Project for the Web, custom formula fields are not currently supported, so weighted progress calculations cannot be configured within the application.

    Otherwise, if your organization tracks progress based on weighted milestones rather than durations or work, consider using Physical % Complete on tasks and then creating custom formulas to calculate weighted project completion. For reference: Physical Percent (%) Complete (task field)

    If this functionality would be valuable for your organization, I encourage you to submit feedback to Microsoft. To ensure your feedback reaches the right teams, I highly recommend submitting your feedback directly to Microsoft Ideas · Community, where the Microsoft product development team can know your requirements and ideas for product improvements. If enough users raise tickets for the same idea, Microsoft may consider adding this feature in the future. 

    Please understand that as a forum user, I do not have access to product design decisions or the development roadmap, but I agree that the ability to define custom weightages for summary task progress would be a useful enhancement.

    Thank you for your patience and understanding. If you have any questions or if I have misunderstood anything, please feel free to reach out.

    Was this answer helpful?

    1 person found this answer helpful.
    0 comments No comments

Your answer

Answers can be marked as 'Accepted' by the question author and 'Recommended' by moderators, which helps users know the answer solved the author's problem.