Hi Jennifer,
Thank you for reaching out.
You can assign both resources to the same task and specify a different amount of work for each resource. Please follow these steps in the Microsoft Project desktop app for Windows:
- Go to View > Resource Sheet.
- Add the following resources:
- Program Management
- System Engineering
- Make sure the Type for both resources is set to Work.
- Return to View > Gantt Chart.
- Select the task.
- On the View tab, enable Details to display the Task Form.
- Right-click inside the Task Form and select Work.
- Enter the following values in the Work field:
- Program Management: 2h
- System Engineering: 6h
- Select OK to apply the assignments.
The task should then show 8 hours of total work, allocated as follows:
- Program Management: 2 hours
- System Engineering: 6 hours
I hope this information is helpful. Please try these steps and let me know how it goes.
Thank you for your time and patience.