Purview DSPM Data Risk Assessment Report Stuck in Processing State and Continuously Extending Completion Date

Lin Xie 10 Reputation points
2026-07-25T23:13:06.0966667+00:00

Product

Microsoft Purview Data Security Posture Management (DSPM) / Data Risk Assessment

Severity

Medium (Business Impact)

Description

We are currently undertaking a Microsoft 365 Copilot readiness assessment and are relying on the Microsoft Purview Data Risk Assessment report as a critical input into our security review and remediation activities.

The assessment was initiated successfully; however, the report has failed to generate and the expected completion date continues to move forward automatically.

Observed timeline:

Original expected completion date: 18 July 2026

Updated expected completion date: 25 July 2026

Current expected completion date: 1 August 2026

The assessment remains in a processing state and no report has been produced.

We are concerned that the report generation process may be stalled or encountering a backend issue.

Business Impact

The report is required to:

Assess organizational data exposure risks

Review oversharing risks across SharePoint, Teams, and OneDrive

Support Microsoft 365 Copilot deployment readiness activities

Develop remediation recommendations and governance controls

The inability to generate this report is delaying our security assessment and implementation planning activities.

Request

Could Microsoft Support please:

Confirm whether the assessment is progressing normally.

Investigate whether the assessment is stuck or has failed in the backend.

Confirm if there are any known service issues affecting DSPM Data Risk Assessments.

Advise whether the assessment should be restarted.

Provide an estimated path forward to obtain the report.

Environment Details

Tenant Name: Office of Sport (NSW Government) Service: Microsoft Purview DSPM / Data Risk Assessment Region: Australia Assessment Status: Processing Current Expected Completion Date: 1 August 2026

Additional Information

The expected completion date has been extended multiple times without producing results:

18 July → 25 July → 1 August

This behaviour suggests the assessment may not be progressing correctly.

Screenshots of the assessment status page can be provided upon request.

Description

We are currently undertaking a Microsoft 365 Copilot readiness assessment and are relying on the Microsoft Purview Data Risk Assessment report as a critical input into our security review and remediation activities.

The assessment was initiated successfully; however, the report has failed to generate and the expected completion date continues to move forward automatically.

Observed timeline:

Original expected completion date: 18 July 2026

Updated expected completion date: 25 July 2026

Current expected completion date: 1 August 2026

The assessment remains in a processing state and no report has been produced.

We are concerned that the report generation process may be stalled or encountering a backend issue.

Business Impact

The report is required to:

Assess organizational data exposure risks

Review oversharing risks across SharePoint, Teams, and OneDrive

Support Microsoft 365 Copilot deployment readiness activities

Develop remediation recommendations and governance controls

The inability to generate this report is delaying our security assessment and implementation planning activities.

Request

Could Microsoft Support please:

Confirm whether the assessment is progressing normally.

Investigate whether the assessment is stuck or has failed in the backend.

Confirm if there are any known service issues affecting DSPM Data Risk Assessments.

Advise whether the assessment should be restarted.

Provide an estimated path forward to obtain the report.

Environment Details

Tenant Name: Office of Sport (NSW Government)
Service: Microsoft Purview DSPM / Data Risk Assessment
Region: Australia
Assessment Status: Processing
Current Expected Completion Date: 1 August 2026

Additional Information

The expected completion date has been extended multiple times without producing results:

18 July → 25 July → 1 August

This behaviour suggests the assessment may not be progressing correctly.

Screenshots of the assessment status page can be provided upon request.

Microsoft Security | Microsoft Purview

Answer recommended by moderator
Lin Xie 10 Reputation points
2026-08-04T01:54:13.0266667+00:00

My default one has also completed, and the ticket is now closed.

Was this answer helpful?

1 person found this answer helpful.
0 comments No comments

0 additional answers

Sort by: Most helpful

Your answer