- Click the Duration field in MS Project.
- Delete e from ewks and type wks (e.g., 2 ewks → 2 wks).
- Press Enter.
If there are many tasks, you can use Ctrl + H (Find and Replace) to replace ewks with wks.
wks = Working weeks (normal project time) ewks = Elapsed weeks (includes weekends and holidays)