What you are showing in your latest screen shot is the assignment information for a particular task. And as I said, there are two ways to get information from Excel - one is with an import map and the other is via VBA. To use an import map for your data you will need to set up 3 separate worksheets in Excel whereas with VBA, the data can be extracted directly from the Excel table you show (i.e. does not need separate worksheets).
Or, you could copy and paste from your Excel table to the Task Information window for each task.
Just a word about managing material resources. In Project there is no quantity control of material resources. You specify the material (Name), the usage basis (e.g. per hour, per cubic meter, per gallon, etc.), and the cost per usage basis (i.e $/cubic meter). There is no max limit on material resources like there is with a work type resource. However, you will be able to see the total cost and total usage of each material via the Resource Usage view.
John