Javier T,
A simple copy and paste isn't going to get you there. What you show in your Excel screen shot appears to be two different types of resources, material and work, although it's not quite clear if the equipment is owned or leased.
There are basically two ways to automate the process of importing your Excel data into Project. One is via an import map. That will require the Excel data to be set up in three separate Worksheets, one for task data, one for resource data, and one for assignment data.
The other method to automate the transfer of Excel data to Project is with VBA.
So, is there a way to do what you want? Yes, but it isn't straightforward.
John