Hi,
A1 = start date and holidays is a named range of dates to exclude
=WORKDAY(A1,30,Holidays)-SUMPRODUCT(--(WEEKDAY(ROW(INDIRECT(A1&":"&WORKDAY(A1,30,Holidays))),2)>5))
If this post answers your question, please mark it as the Answer.
Hello Mike,
That does not work: Try A1 = 5-June-2010. Holidays: 30-June-2010, 6-July-2010, 7-July-2010. Your formula returns 7-July-2010, a holiday. Correct is 8-July-2010.
I suggest to use:
=ThirtyDaysAfter(A1,Holidays)
Function ThirtyDaysAfter(dt As Date, vHolidays As Variant) As Date
Dim vwh(1 To 7, 1 To 2) As Variant
vwh(1, 1) = 0: vwh(1, 2) = 1
vwh(2, 1) = 0: vwh(2, 2) = 1
vwh(3, 1) = 0: vwh(3, 2) = 1
vwh(4, 1) = 0: vwh(4, 2) = 1
vwh(5, 1) = 0: vwh(5, 2) = 1
vwh(6, 1) = 0: vwh(6, 2) = 1
vwh(7, 1) = 0: vwh(7, 2) = 1
ThirtyDaysAfter = Int(add_hours(dt, 30.0001, vwh, vHolidays))
End Function
The function add_hours:
http://sulprobil.com/html/count\_hours.html
Regards,
Bernd